FG Announces Six-Week Partial Closure Of Lagos-Ibadan Expressway For Repairs

Posted by Samuel on Fri 06th Feb, 2026 - tori.ng

The ministry said the closure became necessary to resume critical rehabilitation works earlier suspended on the Lagos-bound section of Kara Bridge following public complaints over prolonged traffic congestion.

 

The Federal Government, through the Federal Ministry of Works, on February 5 announced a six-week partial closure of the Lagos–Ibadan Expressway.

This is to enable repairs on expansion joints at Kara Bridge, Magboro Bridge and Arepo–Punch Bridge. 

The ministry said the closure became necessary to resume critical rehabilitation works earlier suspended on the Lagos-bound section of Kara Bridge following public complaints over prolonged traffic congestion. 

Addressing journalists at Kara Bridge, the Ogun State Federal Controller of Works, Michael Komolafe, apologised to motorists for the inconvenience and assured that improved traffic management arrangements would be put in place to ensure swift and durable repairs. 

Komolafe explained that the expansion joints on the three bridges had deteriorated significantly, posing safety risks and contributing to crashes. He said the Minister of Works, David Umahi, had directed that urgent repairs be carried out. 

He added that work had already been completed on half of the Lagos-bound sections of Magboro and Arepo–Punch bridges, while the remaining portions on the Ibadan-bound side would now be addressed. 

On the scope of work, the contractor and General Manager of CBC Construction Company, Andy Duan, said the repairs would take six weeks, with mobilisation of equipment to be completed over the weekend and full construction expected to begin on Monday, Feb. 9. 

According to him, parts of the expansion joints at Magboro and Arepo–Punch bridges had been completed, while half of the Lagos-bound section at Kara Bridge was already done. 

He said: “At Kara Bridge, we have finished half of it. So we are facing the other half of it. Instead of causing traffic, that’s why we suspended the work temporarily. Now we are getting instructions from the Ministry of Works to resolve this issue. 

“Actually, the condition of the expansion joint for Kara Bridge is very bad and always causing traffic accidents. 

“Before we make the diversion, we are going to bring materials like barriers to protect the temporary working area and put traffic signs, warning signs and warning lights to make sure traffic moves safely and our workers are protected. 

“We are supposed to start immediately, but we are shifting it to Monday. We expect to complete half of each expansion joint within a week. For the Ibadan-bound side, covering three bridges, we will divide the work into phases so each bridge takes about a week.” 

Meanwhile, the Lagos State Sector Commander of the Federal Road Safety Corps, Kehinde Hamzat, assured motorists that measures had been put in place to ensure smooth traffic flow during the construction period. 

He warned against driving against traffic, noting that violators would be sanctioned, and said the repairs were prompted by reports of failing expansion joints that had caused ditches and crashes, particularly on Kara Bridge. 

Hamzat urged motorists to cooperate and exercise patience, describing the closure as a necessary step to improve road safety and infrastructure.

Popular Stories
Things You May Not Know About University of Ibadan... Number One will Shock You
See the Airplane Biafra Legend, Odimegwu Ojukwu Used in Fleeing to Ivory Coast After the Civil War (Photos)
List of Things You Are Entitled to by Law From Your Employer
Wonders! Goat Born With Only Two Legs Spotted Getting Around on Just Its Front Legs (Photos+Video)
See List Of 7 Inventors Killed By Their Inventions


Copyright © 2025 Tori.ng - All rights reserved
Tori.ng is owned and managed by Cyclofoss Technologies Ltd.