FG To Shutdown Third Mainland Bridge For 72 hours, Closes Ibadan-expressway For 48 hours

Posted by Amarachi on Wed 23rd Dec, 2020 - tori.ng

The shutdown will become effective starting from midnight on December 25 to midnight on Tuesday, December 28.

bridge

Third mainland bridge

The Federal government has announced a three days shut down of third mainland bridge in Lagos State and a 48 hours partial closure of the Lagos-Ibadan Expressway.

The shutdown will become effective starting from midnight on December 25 to midnight on Tuesday, December 28.

According to The Federal controller, Olukayode Popoola, the construction works had reached the stage for casting concrete on additional three expansion joints.

“There is going to be total closure of Third Mainland Bridge in order to allow for the casting of three number expansion joints on the Island Bound lane

“The effective date of the closure will be from 12:00 midnight of 25th of December. So people will be allowed to use the Third Mainland Bridge to celebrate Christmas.

“By the time the Christmas is winding down which is 12:00 midnight, we are going to close it so that we will be able to cast the concrete on Saturday the 26th and 27th we cast again.

And we need about 72 hours for this concrete to set. Therefore, the opening will be on the 28th December midnight, that is 72-hour closure.

“This is to prevent vibration of the bridge. If we allow vehicles to be moving on one lane, there is going to be vibrations and the concrete will not set properly,”
he said.

The controller added that all the alternative routes were in good condition and that the traffic regulatory agencies had been deployed to effectively divert and manage traffic to prevent gridlock.

He also appealed to the road users to cooperate with traffic regulatory agencies in other to avoid gridlock.

The controllers also announced a 48 hours partial closure of the Lagos-Ibadan Expressway from Dec. 28 to Dec. 29 to complete some work on a fly over bridge on the project.

“The contractor, Messers Julius Berger wants to install cross beams at Kilometre 16, that is, around MFM,” he said.

He explained that the Piers were already standing on both sides of the road and the contractor was to lay the cross beam on top across the road.

“That area will be cordoned off, there will be closure within that section from 12:00 pm on 28th of December and it will be opened to traffic by 5:00am the following day.

”200 meters to get to that particular location we have diversion and another diversion 200 meters away from that place.

“One lane will be opened to traffic, it is only one lane we are closing to traffic at a time. The first lane that we are going to close is outward Lagos, that is the Ibadan bound carriageway, we will close it on the 28th.

”And then the second day which is 29th, we are moving to the other lane which in inward Lagos. The same 12:00pm to 5:00 am,
” Popoola said.

He also appealed to the public for understanding as he said that the government regrets all the hardship and inconvenience the action would cause.

“We regret all the inconvenience and hardship this might have created,
” he said.

The Third Mainland Bridge in Lagos, has been going through series of repairs and had been partially shut on July 24 for another round of rehabilitation works.

The repair expected to last six months was extended by one month due to the recent #EndSARS protests which extended the completion date from January 2021 to February.